Point Beach Nuclear Power Plant has an immediate need:

Functional Requirements (1R32 Pre-Outage, 11/1/09-2/28/10)

Perform duties required per site technical coordinator for Siemens Alliance contract scope of work to include the following:
1. Review and optimize outage schedule for
a. Generator rewind
b. HP turbine upgrades
c. High-lift valve mod
d. Inlet piping replacement
e. Seal oil system mods

2. Prepare and review detailed contingency plans for above scope of work

3. Review materials delivery plan and optimize staging of tools and materials

4. Prepare laydown plan with Siemens input and coordinate with other outage work

5. Review resource loading for
a. Crane bay
b. Gantry crane
c. Mobile crane
d. Laydown areas

6. Coordinate, prepare, or verify ready FPL/NextEra scope of work in the NextEra/Siemens division of responsibility, to include:
a. Skid pans for coil removal
b. Disposal/asset recovery plans for materials removed from generator
c. Office space, sanitary facilities, LAN and phone connections
d. Training coordination
e. BEC/DZNPS carpenter, laborer, electrical and other support
f. Health physics support to scan and free-release materials
g. Scaffolding and other craft support
h. Scheduler (Primavera specialist)
i. Power rollers, saddles, rotor stands as needed
j. Cribbing, skids and pallets for disassembled parts
k. Forklifts for material handling
l. Insulation removal, asbestos abatement, and reinstallation
m. Support services
i. Welding gases
ii. Temporary power
iii. Ventilation and fans
iv. Lighting
v. Fire protection equipment
n. Support for generator loop test/thermal vision scan

7. Inventory and inspect OEM tooling and rigging

Functional Requirements (1R32 Outage, 3/1/10-5/1/10)
Perform duties required per site technical coordinator for Siemens Alliance contract scope of work to include the following:
1. Provide backshift NextEra supervision and support of Siemens Field Services personnel for
a. Generator rewind
b. HP turbine upgrades
c. High-lift valve mod
d. Inlet piping replacement
e. Seal oil system mods

2. Update schedule as required by outage management/reporting
a. Supervise primavera schedulers and provide technical input
b. Verify that field progress matches reported completions

3. Review daily work progress and report on earned value

4. Provide look-ahead for resources, clearances, testing

5. Maximize staff utilization

6. Provide field safety observations and coaching of Siemens Field Services

7. Ensure compliance with work hour restrictions and manage fatigue

8. Initiate change orders for emergent delays and scope changes

Functional Requirements (2R31 Pre-Outage and Outage, 5/1/10-5/1/11)
Perform duties required per site technical coordinator for Siemens Alliance contract scope of work to include the following:
1. Equivalent scopes of work as performed for 1R32 (above)



[ Back ] [ The Roadtechs Nuclear Job Board ] [ FAQ ] [Edit ] [Mark Position as Filled ]
364 page view(s)

© Copyright - Roadtechs®, LLC. All rights reserved. No reproduction of any part of this website may be sold or
distributed for commercial gain nor shall it be modified or incorporated in any other work, publication, or website.