Roadtechs.com Nuclear Power Plant Outage Schedule (© Roadtechs, LLC)

Name
Begin date
End date
Resources
Angra 1
11/21/16
3/10/17
Bruce 2
12/1/16
2/1/17
Darlington 2
1/2/17
2/3/17
Darlington 3
1/2/17
2/3/17
FitzPatrick
1/16/17
2/16/17
River Bend
RF-19
1/30/17
3/3/17
Bruce 1
1/30/17
3/31/17
Hatch 2
2/6/17
3/21/17
LaSalle 2
2/6/17
3/3/17
Calvert Cliffs 2
2/13/17
3/20/17
St Lucie 2
2/20/17
3/31/17
Robinson
2/22/17
4/4/17
Browns Ferry 2
2/27/17
4/14/17
Susquehanna 2
3/6/17
4/21/17
Perry
3/6/17
4/21/17
Watts Bar 1
3/10/17
4/27/17
Vogtle 1
3/13/17
4/21/17
Indian Point 3
3/13/17
5/26/17
Fermi 2
3/17/17
4/27/17
Brunswick 2
3/20/17
5/8/17
South Texas Project 1
3/20/17
4/28/17
Nine Mile Point 1
3/20/17
4/17/17
McGuire 2
3/27/17
5/1/17
Point Beach 2
3/27/17
4/28/17
Quad Cities 1
3/27/17
4/17/17
Turkey Point 3
3/28/17
5/4/17
ANO 2
4/3/17
6/16/17
Comanche Peak 2
4/3/17
5/10/17
Seabrook
4/3/17
5/12/17
Millstone 2
4/3/17
5/10/17
Palo Verde 2
4/3/17
5/11/17
VC Summer 1
4/4/17
6/12/17
Bruce B 6
4/6/17
8/4/17
Palisades
Plant scheduled to close October 2018.
4/6/17
6/7/17
Pilgrim
Plant scheduled to close on May 31 2019. Last outage scheduled is 2017.
4/10/17
5/10/17
Monticello
4/11/17
5/22/17
Salem 2
4/14/17
5/25/17
Beaver Valley 2
4/17/17
6/9/17
Darlington 1
4/17/17
5/19/17
Waterford 3
4/17/17
5/19/17
Limerick 2
4/17/17
5/25/17
Byron 2
4/18/17
5/23/17
Diablo Canyon 1
4/24/17
7/21/17
Braidwood 2
4/24/17
5/30/17
Ginna
4/24/17
5/24/17
Catawba 1
5/1/17
6/8/17
Bruce B 7
5/5/17
7/6/17
Surry 2
5/8/17
6/13/17
Sequoyah 2
5/8/17
6/23/17
Columbia Generating Station
5/9/17
6/26/17
Clinton
5/16/17
5/29/17
Bruce B 5
6/5/17
8/4/17
Darlington 4
7/3/17
8/4/17
Bruce 4
7/31/17
9/29/17
North Anna 2
8/28/17
10/16/17
Laguna Verde 2
9/1/17
11/30/17
Point Beach 1
9/4/17
10/9/17
McGuire 1
9/11/17
10/19/17
Muehleberg 1
9/13/17
10/11/17
Vogtle 2
9/18/17
10/20/17
Three Mile Island
9/18/17
10/17/17
DC Cook 1
baffle bolt work next 2 outages
9/20/17
10/25/17
Pt. Lepreau 1
9/25/17
11/10/17
Palo Verde 1
10/2/17
11/9/17
Farley 2
10/2/17
10/27/17
Millstone 3
10/2/17
11/9/17
Turkey Point 4
10/2/17
2/2/18
Salem 1
10/6/17
11/16/17
Callaway
10/9/17
12/5/17
Sizewell B
10/9/17
11/17/17
Prairie Island 2
10/16/17
11/30/17
KKL
10/16/17
12/27/17
Watts Bar 2
10/20/17
12/7/17
Comanche Peak 1
10/23/17
11/24/17
Diablo Canyon 2 (projected)
10/23/17
12/6/17
Peach Bottom 3
10/23/17
11/15/17
Oconee 2
10/30/17
12/4/17
Dresden 2
11/2/17
11/28/17
Bruce B 8
1/4/18
3/7/18
Hatch 1
2/8/18
3/9/18
Browns Ferry 3 (projected)
2/9/18
3/30/18
Calvert Cliffs 1
2/15/18
3/16/18
LaSalle 1
2/15/18
3/14/18
Grand Gulf
2/21/18
4/3/18
Brunswick 1
3/5/18
4/20/18
Susquehanna 1
3/5/18
4/19/18
Catawba 2 (projected)
3/5/18
4/12/18
North Anna 1 (projected)
3/5/18
4/23/18
Byron 1
3/6/18
4/10/18
Indian Point 2
There will be more Baffle Bolt work.
3/6/18
5/14/18
Quad Cities 2 (projected)
3/12/18
4/3/18
Laguna Verde 1
3/15/18
5/16/18
ANO 1 (projected)
3/19/18
4/23/18
Beaver Valley 1 (projected)
3/19/18
4/27/18
Fort Calhoun (projected)
Station to close by the end of the year.
3/19/18
5/4/18
Wolf Creek (projected)
3/19/18
5/18/18
Braidwood 1 (projected)
3/20/18
4/12/18
Limerick 1
3/21/18
4/25/18
St Lucie 1 (projected)
3/21/18
4/26/18
Davis Besse 1
3/26/18
5/11/18
Farley 1 (projected)
3/26/18
4/24/18
Palo Verde 3 (projected)
4/2/18
5/14/18
DC Cook 2 (projected)
Extended for unit 2 baffle bolt replacement. also for next 2 outages
4/2/18
7/6/18
South Texas Project 2 (projected)
4/2/18
5/17/18
Hope Creek (projected)
4/9/18
5/8/18
Shearon Harris
4/9/18
5/16/18
Nine Mile Point 2
4/11/18
5/15/18
Surry 1 (projected)
4/16/18
5/15/18
Oconee 3
4/23/18
5/31/18
Clinton (projected)
5/11/18
5/24/18
Angra 1 (projected)
5/15/18
9/3/18
Bruce 3 (projected)
5/21/18
6/20/18
Sequoyah 1 (projected)
Delayed three weeks due to Westinghouse Baffle Bolt work
5/21/18
6/27/18
Muehleberg 1 (projected)
8/9/18
9/6/18
St Lucie 2 (projected)
8/14/18
9/24/18
Robinson (projected)
8/16/18
9/26/18
Watts Bar 1 (projected)
9/3/18
10/19/18
Vogtle 1 (projected)
9/3/18
10/12/18
Fermi 2 (projected)
9/10/18
10/19/18
Oyster Creek (projected)
last outage in fall 2018
9/10/18
10/2/18
South Texas Project 1 (projected)
9/10/18
10/19/18
KKL (projected)
9/10/18
11/21/18
Cooper (projected)
9/17/18
11/23/18
McGuire 2 (projected)
9/17/18
10/22/18
Point Beach 2 (projected)
9/17/18
10/19/18
Turkey Point 3 (projected)
9/19/18
10/26/18
Browns Ferry 1 (projected)
9/21/18
10/23/18
ANO 2 (projected)
9/24/18
12/7/18
Comanche Peak 2 (projected)
9/24/18
10/31/18
Duane Arnold (projected)
9/24/18
10/15/18
Seabrook (projected)
9/24/18
11/2/18
Millstone 2 (projected)
9/24/18
10/31/18
Palo Verde 2 (projected)
9/24/18
11/1/18
VC Summer 1 (projected)
9/26/18
12/4/18
Palisades (projected)
Plant scheduled to close October 2018.
9/28/18
11/29/18
Prairie Island 1 (projected)
10/4/18
11/19/18
Salem 2 (projected)
10/8/18
11/16/18
Beaver Valley 2 (projected)
10/8/18
11/30/18
Waterford 3 (projected)
10/8/18
11/9/18
Peach Bottom 2 (projected)
10/15/18
11/7/18
Diablo Canyon 1 (projected)
10/15/18
1/11/19
Braidwood 2 (projected)
10/16/18
11/21/18
Ginna (projected)
10/16/18
11/15/18
Catawba 1 (projected)
10/22/18
11/29/18
Dresden 3 (projected)
10/22/18
11/13/18
Oconee 1 (projected)
10/26/18
12/5/18
Surry 2 (projected)
10/29/18
12/4/18
Sequoyah 2 (projected)
10/29/18
12/14/18
Bruce 2 (projected)
11/21/18
1/22/19
Darlington 2 (projected)
12/24/18
1/25/19
Darlington 3 (projected)
12/24/18
1/25/19
FitzPatrick (projected)
1/4/19
2/6/19
River Bend (projected)
RF-19
1/21/19
2/22/19
Bruce 1 (projected)
1/21/19
3/22/19
Hatch 2 (projected)
1/28/19
3/12/19
LaSalle 2 (projected)
1/28/19
2/22/19
Calvert Cliffs 2 (projected)
2/4/19
3/11/19
Browns Ferry 2 (projected)
2/15/19
4/4/19
North Anna 2 (projected)
2/19/19
4/9/19
Susquehanna 2 (projected)
2/22/19
4/11/19
Laguna Verde 2 (projected)
2/25/19
5/24/19
Perry (projected)
2/25/19
4/12/19
Point Beach 1 (projected)
2/25/19
4/1/19
Indian Point 3 (projected)
3/4/19
5/17/19
McGuire 1 (projected)
3/4/19
4/11/19
Brunswick 2 (projected)
3/8/19
4/26/19
Nine Mile Point 1 (projected)
3/11/19
4/8/19
Vogtle 2 (projected)
3/11/19
4/12/19
DC Cook 1 (projected)
baffle bolt work next 2 outages
3/14/19
4/18/19
Pt. Lepreau 1 (projected)
3/18/19
5/3/19
Quad Cities 1 (projected)
3/18/19
4/8/19
Palo Verde 1 (projected)
3/25/19
5/2/19
Farley 2 (projected)
3/26/19
4/22/19
Millstone 3 (projected)
3/26/19
5/3/19
Turkey Point 4 (projected)
3/26/19
7/29/19
Bruce B 6 (projected)
3/27/19
7/25/19
Pilgrim (projected)
Plant scheduled to close on May 31 2019. Last outage scheduled is 2017.
4/1/19
5/1/19
Salem 1 (projected)
4/1/19
5/10/19
Callaway (projected)
4/1/19
5/28/19
Sizewell B (projected)
4/1/19
5/10/19
Monticello (projected)
4/1/19
5/10/19
Darlington 1 (projected)
4/8/19
5/10/19
Limerick 2 (projected)
4/8/19
5/16/19
Byron 2 (projected)
4/8/19
5/13/19
Watts Bar 2 (projected)
4/15/19
5/31/19
Comanche Peak 1 (projected)
4/15/19
5/17/19
Bruce B 7 (projected)
4/25/19
6/26/19
Columbia Generating Station (projected)
4/29/19
6/14/19
Bruce B 5 (projected)
5/24/19
7/25/19
Darlington 4 (projected)
6/21/19
7/25/19
Bruce 4 (projected)
7/19/19
9/19/19
Laguna Verde 1 (projected)
9/6/19
11/7/19
Three Mile Island (projected)
9/9/19
10/8/19
Shearon Harris (projected)
9/30/19
11/6/19
Prairie Island 2 (projected)
10/4/19
11/20/19
Peach Bottom 3 (projected)
10/14/19
11/6/19
Oconee 2 (projected)
10/18/19
11/22/19
Dresden 2 (projected)
10/23/19
11/18/19
Bruce B 8 (projected)
12/25/19
2/25/20
Hatch 1 (projected)
1/29/20
2/27/20
Calvert Cliffs 1 (projected)
2/5/20
3/5/20
LaSalle 1 (projected)
2/5/20
3/3/20
Grand Gulf (projected)
2/11/20
3/23/20
Brunswick 1 (projected)
2/21/20
4/9/20
Susquehanna 1 (projected)
2/21/20
4/8/20
Byron 1 (projected)
2/24/20
3/30/20
Indian Point 2 (projected)
There will be more Baffle Bolt work.
2/24/20
5/1/20
Limerick 1 (projected)
3/10/20
4/14/20
Davis Besse 1 (projected)
3/16/20
5/1/20
Nine Mile Point 2 (projected)
3/31/20
5/4/20
Oconee 3 (projected)
4/13/20
5/21/20

Ganttproject (2.7.2 Ostrava (build 1954))ganttproject.biz
12/27/16 - 5:02:39 PM